Assessment of Contaminated Brine Fate and Transport in MB139 at WIPP | |
Kuhlman, Kristopher L.; Malama, Bwalya | |
2014-07-01 | |
出版年 | 2014 |
页数 | 41 |
语种 | 英语 |
国家 | 美国 |
领域 | 地球科学 |
英文摘要 | Following the radionuclide release event of February 14, 2014 at the Waste Isolation Pilot Plant (WIPP), actinide contamination has been found on the walls and floor in Panel 7 as a result of a release in Room 7 of Panel 7. It has been proposed to decontaminate Panel 7 at the WIPP by washing contaminated surfaces in the underground with fresh water. A cost-effective cleanup of this contamination would allow for a timely return to waste disposal operations at WIPP. It is expected that the fresh water used to decontaminate Panel 7 will flow as contaminated brine down into the porosity of the materials under the floor â the run-of-mine (ROM) salt above Marker Bed 139 (MB139) and MB139 itself â where its fate will be controlled by the hydraulic and transport properties of MB139. Due to the structural dip of MB139, it is unlikely that this brine would migrate northward towards the Waste-Handling Shaft sump. A few strategically placed shallow small-diameter observation boreholes straddling MB139 would allow for monitoring the flow and fate of this brine after decontamination. Additionally, given that flow through the compacted ROM salt floor and in MB139 would occur under unsaturated (or two-phase) conditions, there is a need to measure the unsaturated flow properties of crushed WIPP salt and salt from the disturbed rock zone (DRZ). |
URL | 查看原文 |
来源平台 | US Department of Energy (DOE) |
引用统计 | |
文献类型 | 科技报告 |
条目标识符 | http://119.78.100.173/C666/handle/2XK7JSWQ/6438 |
专题 | 地球科学 |
推荐引用方式 GB/T 7714 | Kuhlman, Kristopher L.,Malama, Bwalya. Assessment of Contaminated Brine Fate and Transport in MB139 at WIPP,2014. |
条目包含的文件 | 条目无相关文件。 |
除非特别说明,本系统中所有内容都受版权保护,并保留所有权利。
修改评论