Ivanhoe’s Kamoa-Kakula concentrator beating design throughput target
admin
2021-09-30
发布年2021
语种英语
国家国际
领域地球科学
正文(英文)
Members of Kamoa-Kakula’s construction team. Image from Ivanhoe.

Ivanhoe Mines (TSX: IVN) says that after the first phase of concentrator construction, the facility is exceeding designed throughput rates, treating 320,000 tonnes of ore in the month ending Sept. 20.

Design capacity is 315,000 tonnes per month with a head grade of 6% copper. Copper production for the month was a record 16,010 tonnes.

The company says the phase one concentrator, located in the Democratic Republic of Congo, will treat 3.8 million tonnes of ore annually. The mill treated 384.000 tonnes of ore grading 5.6% copper in September, including 141,000 grading 7.32% copper from the centre of the Kakula mine. Surface stockpiles have reached 3.66 million tonnes grading 4.73% copper.

The average floated concentrate grade was 55.7% copper, up from 48% in August. A total of 46,764 tonnes of copper have been produced in the first nine months of 2021.

The daily floated copper recovery rate was 85.1% during the month, up from 83% in August. A daily record copper recovery rate of 88.3% was achieved on September 12, and a daily floated copper production record of 721 tonnes was set on Sept. 15. A daily record high milling rate of 12,596 tonnes (the nameplate capacity is 10,500 t/d) and a daily crushing record of 14,778 tonnes was achieved on September 27.

“There are a number of additional adjustments being incorporated into the phase one processing circuit, which will enable the concentrator to achieve better results in the next quarter. These adjustments, which also will be incorporated into the phase two processing circuit, should position us to achieve 2021 copper production in the upper end of our previous guidance of 80,000 to 95,000 tonnes. This gives us the confidence to raise the range to 85,000 to 95,000 tonnes,” said Kamoa Copper CEO Mark Farren in a media statement.

More mill capacity

The commissioning of an additional concentrate filter is being fast tracked in the mill. This will take advantage of copper feed grades and milling rates in excess of design. The extra filter is to be fully operational in early October. The concentrator is then expected to produce more than the design capacity of 200,000 tonnes of copper annually during  phase one operation.

Phase two construction is over 50% complete, and the immediate focus is on structural steel, mechanical, piping and platework erection and installation. The second plant will have an annual capacity of 3.8 million tonnes, matching the phase one plant.

A study is also underway for the third phase of concentrator construction. The work will address mining production capacity and costs, including expanded facilities at the Kansoko, Kamoa North, Bonanza zone, and Kakula West deposits. The optimal sizing of the phase three mill will also be decided.

The Kamoa-Kakula copper project is a joint venture of operator and 39.6% owner Ivanhoe Mines and partners Zijin Mining Group (39.6%), Crystal River Global (0.8%), and the Democratic Republic of Congo government (20%).

(This article first appeared in the Canadian Mining Journal)

URL查看原文
来源平台Minging.com
文献类型新闻
条目标识符http://119.78.100.173/C666/handle/2XK7JSWQ/338064
专题地球科学
推荐引用方式
GB/T 7714
admin. Ivanhoe’s Kamoa-Kakula concentrator beating design throughput target. 2021.
条目包含的文件
条目无相关文件。
个性服务
推荐该条目
保存到收藏夹
查看访问统计
导出为Endnote文件
谷歌学术
谷歌学术中相似的文章
[admin]的文章
百度学术
百度学术中相似的文章
[admin]的文章
必应学术
必应学术中相似的文章
[admin]的文章
相关权益政策
暂无数据
收藏/分享
所有评论 (0)
暂无评论
 

除非特别说明,本系统中所有内容都受版权保护,并保留所有权利。