Setting sail: EU priorities to deliver North Seas offshore wind
Simon Skillings Lisa Fischer
2021-07-20
出版年2021
国家欧洲
领域气候变化
英文摘要

The European Commission has recognised the critical role that offshore renewable resources, especially offshore wind, will play in enabling the Union to become climate neutral by 2050. It has set ambitious deployment targets as part of the EU Strategy on Offshore Renewable Energy.

Modelling undertaken by E3G and researchers from Imperial College London suggests an estimated €30-60bn in savings are available in the period out to 2050 from establishing an offshore grid that connects offshore wind capacity and links the power systems of coastal countries, including non-EU countries.[1] In addition to cost savings, this approach would reduce the number of onshore connections and their associated environmental impacts.

This briefing summarises the modelling and sets out four ‘critical path’ recommendations if the EU is to realise these benefits:

  1. The TEN-E Regulation and the Renewable Energy Directive should be used to establish the process for delivering an integrated offshore network. This should include new mechanisms for grid planning and for allocating the costs and benefits of offshore assets. There should be a specific requirement on member states to co-operate to define the integrated offshore grid that will allow them to deliver their offshore wind ambitions at least cost. Initial network plans should support delivery of the EU’s 2030 ambitions.
  2. The European Scientific Advisory Board on Climate Change, which will be established under the recently approved EU Climate Law, should be requested to provide independent science-based advice on the key assumptions that should be used to develop the network plan. It should also maintain oversight on the entire process to ensure outcomes are aligned with the climate neutrality pathway. This is because the optimal deployment of offshore resources depends critically on a wide range of assumptions about the future use of gas and the nature of energy consumption.
  3. The EU and UK should commit to proceed with a shared offshore network project that connects offshore wind farms (so-called ‘hybrid interconnector’) by the end of 2021 such that it becomes operational before the end of 2029. There are significant benefits for both the EU and UK from ensuring the offshore power networks connects offshore renewable resources and onshore power networks of both parties. With little time available, a political commitment is required to inject urgency and establish a process to realise the benefits. This commitment should be underpinned by a new memorandum of understanding to develop the regulatory framework and delivery processes by the end of 2023.
  4. The EU should establish new mechanisms to enable and promote Europe-wide buy in to the North Seas project. Participation of all stakeholders including those outside the energy industry and not in countries with a North Seas coast is appropriate given the overall strategic importance of the project to EU climate targets and economic growth.

Read the briefing in full.


[1] Compared to the situation where countries establish independent offshore networks.

URL查看原文
来源平台E3G
文献类型科技报告
条目标识符http://119.78.100.173/C666/handle/2XK7JSWQ/334298
专题气候变化
推荐引用方式
GB/T 7714
Simon Skillings Lisa Fischer. Setting sail: EU priorities to deliver North Seas offshore wind,2021.
条目包含的文件
条目无相关文件。
个性服务
推荐该条目
保存到收藏夹
查看访问统计
导出为Endnote文件
谷歌学术
谷歌学术中相似的文章
[Simon Skillings Lisa Fischer]的文章
百度学术
百度学术中相似的文章
[Simon Skillings Lisa Fischer]的文章
必应学术
必应学术中相似的文章
[Simon Skillings Lisa Fischer]的文章
相关权益政策
暂无数据
收藏/分享
所有评论 (0)
暂无评论
 

除非特别说明,本系统中所有内容都受版权保护,并保留所有权利。